Installation, Operation, and Maintenance Manual

You can download your own copy of the most up-to-date IOM Manual below.

Installation, Operation, and Maintenance Manual

Revision Date Revision Items
8-24

General updates to Table of Contents and page organization

5-28-24

Changed the bolt hole sizes for the B.O.S.S. fitting and the Stainless Steel fittings. Changed from 9/16″ to 5/8″

5-24

Added, “Make sure the IMFO neck is supported and the maximum concrete pad projection is 2” under the IMFO neck. (See pictures below) Make sure there are no valves or heavy piping hanging off the IMFO.” to page 3.

4-2024

Fixed page numbering issues.

3-2024

All new reformatted IOM Manual.
Added updated Venting Matrix with fume tight update
Updated Reverse Float Level Gauge drawing to remove internal perforated pipe and support.

9-8-23

Updated offloading instructions regarding foamed tanks and wooden cradles.

8-2-23

Clarified that seismic systems are different in many cases. Added “The material, type of clip, quantity of clips, cables, etc. may vary. Please consult the calculations that were sent with your system or contact Poly Processing with any questions.”

It is critical to reference the calculations for your specific seismic system and tank.

6/2023

Added a link on page 40.

10/2022

Added verbiage regarding Enhanced Bellows Transition Fitting – Make sure all all bolts of the piping assembly are properly torqued including the primary tank fitting, expansion joint connections, and the threaded coupler if a B.O.S.S. fitting is installed. Go to www.polyprocessing.com/safetankinstall for SAFE-Tank installation videos.

8/2022

Added links to more IOM information on Page 40

2/2022

Updated cover and links to Installation, Operation, and Maintenance Manual

9/2021

Added notes section on back page

6/2021

Updated RFLG page

3/2021

Included new SAFE-Tank and Transition fitting instructions and landing page link

Details

11/2020

Updated Bellows Transition Fitting Installation instructions and added polyprocessing.com/safetankinstall for SAFE-Tank Installation Instructions page with video installation instructions.

10/2020

Added text on page 23 regarding the need for a crane or boom truck to set the transition fitting in place. Set the transition fitting before the crane or boom truck leaves the installation

09/2020

Added note regarding flexible connectors

08/2020

Updated IMFO base information. Updated flexible connection section with EPDM expansion joints and updated guidelines

07/10/2020

Updated reference page numbers for flexible connections and piping support

05/20/2020

Updated seismic drawings and instructions

03/03/2020

Added verbiage regarding butterfly valve installation

02/13/2020

Added : Reverse Float system may not include internal downpipe and pipe support if ordered without it. Check with your sales contact to see if it was included in the order

07/30/2019

Updated the Bellows Transition Fitting instructions

12/01/2018

Added link to PPC IOM Manual on front cover

11/06/2017

Added “Venting charts based on recommendation and criteria from Venting Design for ACFM Technical Paper”, page 4

10/01/2017

Added current revision date on all pages

7/01/2017

Added new Bellows Transition Fitting installation information, pages 22-24

6/05/2017

Added IMFO support information, pages 3 & 10

6/01/2017

Corrected ladders pages

5/01/2017

Added calibration tape instructions, page 18

If you need additional assistance or have a question about installation, please contact customer support.